Multiple Choice
Table 3.2
Time (days)
-Using Table 3.2,if the project manager wants at least a 98% probability that the project will be completed on or before the due date,what is the shortest project due date that will satisfy the manager? You will need to refer to a standard normal table to answer the question.
A) less than or equal to 28 days
B) greater than 28 days but less than or equal to 30 days
C) greater than 30 days but less than or equal to 32 days
D) greater than 32 days
Correct Answer:

Verified
Correct Answer:
Verified
Q72: Table 3.5<br> <span class="ql-formula" data-value="\begin{array}
Q73: Table 3.4<br> <span class="ql-formula" data-value="\begin{array}
Q74: Table 3.10<br>You are responsible for managing
Q75: Table 3.4<br> <span class="ql-formula" data-value="\begin{array}
Q75: The activities along the critical path determine
Q78: Table 3.12<br>You are responsible for managing
Q79: A critical path is the sequence of
Q85: The optimistic time is the probable time
Q101: Free slack is the amount of time
Q104: Many small incremental changes to project objectives,