Multiple Choice
Table 3.10
You are responsible for managing a project with the following activities
(times are given in weeks) .
-Using Table 3.10,what is the probability of completing the project in 17 weeks or less? You will need to refer to a standard normal table to answer the question.
A) less than or equal to 40%
B) greater than 40% but less than or equal to 55%
C) greater than 55% but less than or equal to 70%
D) greater than 70%
Correct Answer:

Verified
Correct Answer:
Verified
Q70: Table 3.3<br> <span class="ql-formula" data-value="\begin{array}
Q72: Table 3.5<br> <span class="ql-formula" data-value="\begin{array}
Q73: Table 3.4<br> <span class="ql-formula" data-value="\begin{array}
Q75: Table 3.4<br> <span class="ql-formula" data-value="\begin{array}
Q75: The activities along the critical path determine
Q76: Table 3.2<br>Time (days)<br> <span class="ql-formula"
Q78: Table 3.12<br>You are responsible for managing
Q83: Projects cannot have more than one critical
Q85: The optimistic time is the probable time
Q101: Free slack is the amount of time