Table 310
You Are Responsible for Managing a Project with the the Following

Question 74

Multiple Choice

Table 3.10
You are responsible for managing a project with the following activities
(times are given in weeks) .
 Activity  Optimistic  Time  Most Likely  Time  Pessimistic  Time  Immediate  Predecessor(s)   A 2514 B 81114 C 579 A  D 6912 A  E 135 D,B \begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Optimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Most Likely } \\\text { Time }\end{array} & \begin{array} { c } \text { Pessimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 2 & 5 & 14 & \cdots \\\text { B } & 8 & 11 & 14 & \cdots \\\text { C } & 5 & 7 & 9 & \text { A } \\\text { D } & 6 & 9 & 12 & \text { A } \\\text { E } & 1 & 3 & 5 & \text { D,B } \\\hline\end{array}
-Using Table 3.10,what is the probability of completing the project in 17 weeks or less? You will need to refer to a standard normal table to answer the question.


A) less than or equal to 40%
B) greater than 40% but less than or equal to 55%
C) greater than 55% but less than or equal to 70%
D) greater than 70%