Multiple Choice
Table 3.4
-Using Table 3.4,of the following activities,which one has a slack value greater than zero weeks?
A) Activity B
B) Activity C
C) Activity K
D) Activity N
Correct Answer:

Verified
Correct Answer:
Verified