    The Primary Purpose of the Contract Modification Procedure in the Agreement
Solved

The Primary Purpose of the Contract Modification Procedure in the Agreement

Question 79

Question 79

True/False

The primary purpose of the contract modification procedure in the agreement between the owner and the GC is to allow change orders.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q70: The owner is required to provide payment

Q71: What is contained in the program of

Q72: The shop drawings are prepared by the<br>A)structural

Q73: Explain the purposes of the three surety

Q74: The construction drawings of a building project

Q75: List the important items contained in a

Q76: In MasterFormat, Division 02 refers to<br>A)Procurement and

Q77: Shop drawings are prepared during the design

Q78: The project delivery method that should ensure

Q80: Establishing the project's economic feasibility and its

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines