A Machined Part Is Returned to the Drilling Department for Rework.The

Question 66

Multiple Choice

A machined part is returned to the drilling department for rework.The additional labor that is used to correct the quality problem with the part is:


A) a prevention cost.
B) an appraisal cost.
C) an internal failure cost.
D) an external failure cost.

Correct Answer: