Multiple Choice
Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the BEST statement.
A) The project is further ahead of budget from weeks 36 through 40 than from weeks 8 through 12.
B) The project never experiences negative variance.
C) The project is further behind budget from weeks 0 through 16 than from 24 through 40.
D) The project is in a constant state of positive variance.