Multiple Choice
A measurement process that determines the project goals and then the degree to which the actual performance lives up to these goals is:
A) A metric system.
B) Goal-performance linkage.
C) Five degrees of separation.
D) Gap analysis.
Correct Answer:

Verified
Correct Answer:
Verified