    Use the Earned Value Table to Determine the Estimated Time
Solved

Use the Earned Value Table to Determine the Estimated Time

Question 86

Question 86

Multiple Choice

Use the earned value table to determine the estimated time to completion given the indicated state of the project. Use the earned value table to determine the estimated time to completion given the indicated state of the project.   A)  35 days B)  37 days C)  39 weeks D)  41 weeks


A) 35 days
B) 37 days
C) 39 weeks
D) 41 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q4: Planned value is:<br>A)The total budget for the

Q16: In earned value management,schedule variance is defined

Q69: The earned value divided by the actual,cumulative

Q72: Take the factors considered by earned value

Q84: Use this earned schedule table to determine

Q84: Take the factors considered by earned value

Q86: The closer to completion a project gets,the

Q87: What are the problems with milestones as

Q88: Use the information in the table regarding

Q105: A project manager that uses milestones as

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines