menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 1
  4. Exam
    Exam 13: Project Evaluation and Control
  5. Question
    A Project Manager That Uses Milestones as a Project Control
Solved

A Project Manager That Uses Milestones as a Project Control

Question 105

Question 105

Multiple Choice

A project manager that uses milestones as a project control device is using a:


A) Proactive control system.
B) Predictive control system.
C) Feedback control system.
D) Reactive control system.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q97: An unmotivated team is a key success

Q98: Measurement mechanisms should include a clear definition

Q99: Use the earned value table for

Q100: Geoff coolly surveyed his earned value

Q101: Use the earned value table to

Q102: Earned value management is also known as:<br>A)The

Q103: The classic project S-curve is a plot

Q104: Duration (weeks)<br> <span class="ql-formula" data-value="\begin{array}

Q106: Use this earned schedule table to

Q107: What is the cost variance of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines