A Project Is Represented by the Activity Durations (In Days

Question 78

Multiple Choice

A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many project buffers are needed if this project is managed using critical chain methodology? A project is represented by the activity durations (in days, estimated at 90% likelihood of completion)  and precedence requirements shown in the table. How many project buffers are needed if this project is managed using critical chain methodology?   A)  0 B)  1 C)  2 D)  3


A) 0
B) 1
C) 2
D) 3

Correct Answer:

verifed

Verified