Multiple Choice
Wayne and Garth are engaged in XP and are constantly streamlining the design and improving the code.In XP terminology,they are engaged in:
A) Scrumming.
B) Refactoring.
C) Sprinting.
D) Time boxing.
Correct Answer:

Verified
Correct Answer:
Verified