Multiple Choice
A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the expected completion time of the project?
A) 32 days
B) 33 days
C) 34 days
D) 35 days
Correct Answer:

Verified
Correct Answer: