Multiple Choice
A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the standard deviation of the project's critical path?
A) 1.33 days
B) 1.56 days
C) 1.25 days
D) 1.75 days
Correct Answer:

Verified
Correct Answer:
Verified
Q3: The amount of time an activity may
Q29: What is the background of CPM and
Q38: Use the information in the table to
Q40: Use the values in the table to
Q41: At a merge point in a forward
Q41: Use the information in the table to
Q44: The variance of an activity is given
Q68: One approach to reducing project length would
Q73: Based on the activity network pictured,what is
Q81: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5361/.jpg" alt=" -Activities C,D,and E