-Activities C,D,and E in the Project Represented by the Network

Question 81

Multiple Choice

  -Activities C,D,and E in the project represented by the network are to be hammocked.What are the late start and early finish times of the hammock activity? A)  6, 24 B)  6, 26 C)  8, 24 D)  8, 26
-Activities C,D,and E in the project represented by the network are to be hammocked.What are the late start and early finish times of the hammock activity?


A) 6, 24
B) 6, 26
C) 8, 24
D) 8, 26

Correct Answer: