Multiple Choice
A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the late finish for the Plant Posts activity?
A) 13.3 days
B) 8 days
C) 20.83 days
D) 22 days
Correct Answer:

Verified
Correct Answer:
Verified
Q19: An activity has a pessimistic time that
Q33: At a burst point in a backward
Q44: In general,the better candidates for shortening are:<br>A)Early
Q47: The overall effect of laddering activities is
Q52: The BEST candidate activities for shortening the
Q67: Construct a network using the information in
Q68: Compute early and late start and finish
Q74: A gentleman farmer maniacally works on academic
Q75: Project Test Bank is composed of activities
Q96: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5361/.jpg" alt=" -Use the network