Multiple Choice
In general,the better candidates for shortening are:
A) Early tasks opposed to later tasks.
B) Later tasks opposed to early tasks.
C) Merge tasks opposed to burst tasks.
D) Burst tasks opposed to merge tasks.
Correct Answer:

Verified
Correct Answer:
Verified