Multiple Choice
Assuming a beta distribution is being used, if the most optimistic time for an activity decreases by 12 days, what will happen to the expected time for that activity?
A) It will decrease by 12 days.
B) It will increase by 2 days.
C) It will decrease by 2 days.
D) It will remain the same.
Correct Answer:

Verified
Correct Answer:
Verified
Q90: Describe four stages of development process.
Q91: If one activity along the critical path
Q92: _ is the shortest time in which
Q93: To calculate the probability of completing a
Q96: In monitoring a project, negative slack indicates
Q97: Why is knowing the critical path in
Q98: All activities on the critical path must
Q99: If a project has multiple critical paths,
Q100: When using the beta distribution for estimating
Q120: Why do managers want to know the