If a Project Has Multiple Critical Paths, Which of the Following

Question 99

Multiple Choice

If a project has multiple critical paths, which of the following variances should be used in analyzing project completion time probabilities?


A) the sum of the variances for all critical paths
B) the critical path with the smallest variance
C) the average variance of the critical paths
D) the critical path with the largest variance

Correct Answer: