Multiple Choice
When using the beta distribution for estimating activity times,
A) the most likely time estimate can be positioned anywhere between the optimistic and pessimistic time estimates.
B) the most likely time estimate becomes the mean of the distribution.
C) we assume that the standard deviation is one- third the range between the optimistic and pessimistic time estimates.
D) an advantage is that the mode of the distribution is always equidistant from the end points of the distribution.
Correct Answer:

Verified
Correct Answer:
Verified
Q95: Assuming a beta distribution is being used,
Q96: In monitoring a project, negative slack indicates
Q97: Why is knowing the critical path in
Q98: All activities on the critical path must
Q99: If a project has multiple critical paths,
Q101: Free slack is the amount of time
Q102: Standard computerized scheduling packages are rarely used
Q103: Each activity in the work breakdown structure
Q104: Many small incremental changes to project objectives,
Q105: The _ is the shortest time in