Multiple Choice
Table 5.2
High Tech, Inc. is producing two types of products: A and B. Both are produced at the same sawing operation. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic) . The demand forecasts, batch sizes (units/batch) , processing times (hr/unit) , and setup times (hr/batch) follow.
The sawing machines operate on two 8-hour shifts, 5 days per week, and 50 weeks per year. The manager wants to maintain a 10 percent capacity cushion.
-Using the information from Table 5.2, what is the minimum total number of hours required of sawing equipment for the next year?
A) less than 85,000 hours
B) more than 85,000 but less than 95,000
C) more than 95,000 but less than 105,000
D) more than 105,000 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q92: The maximum output that can reasonably be
Q93: Many alternative strategies are available for the
Q94: If a system is well balanced, which
Q95: Musk L. Flexor owns a hot tub
Q96: Larry's Wickets, Inc. is producing two types
Q98: Diseconomies of scale refers to situations where
Q99: Which one of the following statements about
Q100: The _ time for a specific item
Q101: Describe the fundamental logic of the theory
Q111: Utilization is the degree to which equipment,