The need to delay activities requiring more funding to later stages of a project is an example of the following constraint(s) :
A) technical requirements and specifications.
B) preferences and policies.
C) safety and efficiency.
D) resource availability.
Correct Answer:

Verified
Correct Answer:
Verified