    A Finish- To- Start Dependency Indicates That the Completion of the Successor
Solved

A Finish- To- Start Dependency Indicates That the Completion of the Successor

Question 61

Question 61

True/False

A finish- to- start dependency indicates that the completion of the successor depends on the beginning of the predecessor.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q56: A _dependency indicates that the start of

Q57: Project scheduling is the process of defining

Q58: A PBS is the output that results

Q59: _is a scheduling technique that requires greater

Q60: _is the time delay between completion of

Q62: A network diagram is a schematic display

Q63: Too much detail of the work packages

Q64: A WBS dictionary:<br>A)is part of the project

Q65: The need to delay activities requiring more

Q66: An activity has well- defined _ steps.

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines