Multiple Choice
A WBS dictionary:
A) is part of the project scope statement.
B) is only needed in the planning phase.
C) provides details about the individual components of the WBS.
D) is not used much, as all the information can be looked up on the Web.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q59: _is a scheduling technique that requires greater
Q60: _is the time delay between completion of
Q61: A finish- to- start dependency indicates that
Q62: A network diagram is a schematic display
Q63: Too much detail of the work packages
Q65: The need to delay activities requiring more
Q66: An activity has well- defined _ steps.
Q67: Budgetary estimates can vary by as much
Q68: _estimates vary from +25% to - 10%.
Q69: Subcomponents of control accounts are referred to