Multiple Choice
The scope baseline includes:
A) the project workbook and the WBS.
B) the baseline project plan, the activity list, and the WBS.
C) the project charter, and all project related documentation.
D) the project scope statement, the WBS, and the WBS dictionary.
Correct Answer:

Verified
Correct Answer:
Verified