    A ____________Dependency Indicates That the Start of a Successor Depends
Solved

A ____________Dependency Indicates That the Start of a Successor Depends

Question 56

Question 56

Short Answer

A ____________dependency indicates that the start of a successor depends on the start of the predecessor.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q51: Schedules are:<br>A)rarely perfect.<br>B)useless.<br>C)easy to develop.<br>D)made to be

Q52: The scope baseline includes:<br>A)the project workbook and

Q53: The estimation phases of project progress, in

Q54: Budgetary estimates have the greatest variation.

Q55: Lists of activities from prior projects are

Q57: Project scheduling is the process of defining

Q58: A PBS is the output that results

Q59: _is a scheduling technique that requires greater

Q60: _is the time delay between completion of

Q61: A finish- to- start dependency indicates that

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines