Short Answer
A ____________dependency indicates that the start of a successor depends on the start of the predecessor.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q51: Schedules are:<br>A)rarely perfect.<br>B)useless.<br>C)easy to develop.<br>D)made to be
Q52: The scope baseline includes:<br>A)the project workbook and
Q53: The estimation phases of project progress, in
Q54: Budgetary estimates have the greatest variation.
Q55: Lists of activities from prior projects are
Q57: Project scheduling is the process of defining
Q58: A PBS is the output that results
Q59: _is a scheduling technique that requires greater
Q60: _is the time delay between completion of
Q61: A finish- to- start dependency indicates that