Multiple Choice
The estimation phases of project progress, in decreasing order, are:
A) definitive estimates, order of magnitude estimates, and budgetary estimates.
B) budgetary estimates, order of magnitude estimates, and definitive estimates.
C) order of magnitude estimates, budgetary estimates, and definitive estimates.
D) order of magnitude estimates, definitive estimates, and budgetary estimates.
Correct Answer:

Verified
Correct Answer:
Verified
Q48: When determining the sequence of activities, the
Q49: A product breakdown structure is also referred
Q50: ADM is better than PDM for illustrating
Q51: Schedules are:<br>A)rarely perfect.<br>B)useless.<br>C)easy to develop.<br>D)made to be
Q52: The scope baseline includes:<br>A)the project workbook and
Q54: Budgetary estimates have the greatest variation.
Q55: Lists of activities from prior projects are
Q56: A _dependency indicates that the start of
Q57: Project scheduling is the process of defining
Q58: A PBS is the output that results