Multiple Choice
Errors made when estimating the expecting or actual performance of the project, resulting in an inaccurate picture of the project status, happen during the:
A) planning process.
B) control process.
C) initiation process.
D) execution process.
Correct Answer:

Verified
Correct Answer:
Verified