A Method Used for Determining the Sequence of Task Activities

Question 59

Multiple Choice

A method used for determining the sequence of task activities that directly affect the completion of a project is called:


A) activity sequence determination.
B) critical path method.
C) critical activity method.
D) program evaluation and review technique.

Correct Answer:

verifed

Verified