Multiple Choice
A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task is called:
A) critical path method.
B) OPR method.
C) program evaluation and review technique.
D) expected completion time analysis.
Correct Answer:

Verified
Correct Answer:
Verified