True/False
A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task is called OPR method.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q48: The project management core area including communications
Q49: Increases in project scope are_ for IT
Q50: The project management core area including activity
Q51: The project management core area including cost
Q52: Information systems project failures can take place
Q54: There are now a variety of project
Q55: Failure to correctly estimate costs, time, or
Q56: A diagram that shows the ordering of
Q57: There are _ major project management process
Q58: A technique that uses optimistic, pessimistic, and