Multiple Choice
A diagram that shows the ordering of activities by connecting predecessor and successor tasks is called a:
A) Gantt chart.
B) Work breakdown structure.
C) Predecessor- successor diagram.
D) Network diagram.
Correct Answer:

Verified
Correct Answer:
Verified