Question 29

Multiple Choice

A project contains activities D and K.Activity D has 5 hours of slack, and activity K has 7 hours of slack.If activity D is delayed 4 hours, activity K is delayed 6 hours, and these are the only delays, then the overall effect of these delays is to delay the minimum project completion time by:


A) 0 hours.
B) 2 hours.
C) 11 hours.
D) The overall delay cannot be determined with only this information.

Correct Answer: