Multiple Choice
Let Ti = normal completion time for task iRi = crash completion time for task i Ci = normal cost for task i
Hi = crash cost for task i
Xi = start time for task i
Yi = amount of time by which task i is to be crashed.
What is the objective function of a linear programming model for project crashing?
A) all i Yi(Hi - Ci) /(Ti - Ri)
B) all i on critical path Yi(Hi - Ci) /(Ti - Ri)
C) all i XiYi
D) all i YiHi
Correct Answer:

Verified
Correct Answer:
Verified