The Probabilistic Approach Characterized by PERT Does Not Use

Question 32

Multiple Choice

The probabilistic approach characterized by PERT does not use:


A) optimistic activity times.
B) median activity times.
C) pessimistic activity times.
D) most likely activity times.

Correct Answer:

verifed

Verified

Unlock this answer now