Activity T has a single immediate predecessor, activity S.However, T may actually be initiated anytime after S is 50% complete.Can this situation be accommodated using standard project scheduling techniques? Explain.
Correct Answer:

Verified
(Yes, this situation may be handled.Mere...View Answer