Multiple Choice
Which statement does not represent a set of constraints for a linear programming approach to project crashing?
A) There is a limit to the time reduction for each activity.
B) No activity can be reduced more than its slack time.
C) Activity start time must be greater than the finish time of all immediate predecessors.
D) The project must be completed by the deadline (or within budget) .
Correct Answer:

Verified
Correct Answer:
Verified
Q33: The critical path shows the earliest project
Q34: Let T<sub>i</sub> = normal completion time
Q35: A Gantt chart, by definition, does not
Q36: Ajax is about to embark on
Q37: What type of distribution does PERT assume
Q39: A PERT/CPM network can be represented as
Q40: Activity T has a single immediate predecessor,
Q41: A project consists of the following
Q42: In the PERT probabilistic approach, statisticians have
Q43: Consider the following activity schedule chart