Ajax Is About to Embark on a Project Involving the Design

Question 36

Essay

Ajax is about to embark on a project involving the design, manufacture, and introduction of a new microwave oven.The first three activities and the immediate predecessors are:  Activity  Predecessor  A  Prototype Design  none  B  Acquisition of Materials  A  C  Prototype Construction  B \begin{array}{lcc}&\text { Activity } &\text { Predecessor }\\\text { A } & \text { Prototype Design } & \text { none } \\\text { B } & \text { Acquisition of Materials } & \text { A } \\\text { C } & \text { Prototype Construction } & \text { B }\end{array}
However, it has not yet been decided whether the prototype materials will be purchased from a vendor (taking two weeks) or produced in another Ajax division (four weeks).What are the implications of this regarding usage of any standard project scheduling technique?

Correct Answer:

verifed

Verified


(PERT/CPM cannot accommodate "either/or...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions