Multiple Choice
Activities K,M,and S immediately follow activity H,and their latest start times are 14,18,and 11.The latest finish time for activity H
A) is 11.
B) is 14.
C) is 18.
D) cannot be determined.
Correct Answer:

Verified
Correct Answer:
Verified