menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Management Science Quantitative Approach
  4. Exam
    Exam 9: Project Scheduling: Pertcpm
  5. Question
    Which of the Following Is Always True About a Critical
Solved

Which of the Following Is Always True About a Critical

Question 40

Question 40

Multiple Choice

Which of the following is always true about a critical activity?


A) LS = EF
B) LF = LS
C) ES = LS
D) EF = ES

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q35: Consider a project that has been modeled

Q36: For an activity with more than one

Q37: The latest finish time for an activity

Q38: The variance in the project completion time

Q39: Activities G,P,and R are the immediate predecessors

Q41: The project manager should monitor the progress

Q42: For the project represented below,determine the earliest

Q43: Consider the following PERT/CPM network with estimated

Q44: A project has the following activities,precedence relationships,and

Q45: Marcy Fetter,a staff analyst at the Los

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines