Multiple Choice
Assume the weighted-average accumulated expenditures for the construction project are $2,900,000. The amount of interest cost to be capitalized during 2014 is
A) $261,000.
B) $276,000.
C) $300,000.
D) $336,000.
Correct Answer:

Verified
Correct Answer:
Verified