Multiple Choice
Given the following information at week 12 of a 54-week project:
PV = 1,200 hours
EV = 1,400 hours
AC = 1,000 hours
Schedule variance percent SV%) and cost variance percent CV%) , respectively, would be:
A) -14.29%, -33.33%
B) +14.29%, +33.33%
C) +16.67%, +28.57%
D) -16.67%, -28.57%
E) None of these, the answer is: ________________ show your work)