Given the Following Information About a Project

Question 9

Multiple Choice

Given the following information about a project:
EV = $20,000
PV = $15,000
AC = $25,000
BAC = $40,000
Estimated Duration = 6 months
Assuming this is the only information available, which of these can we legitimately conclude about the project?


A) Time Estimate at Completion EACtime) ) = 4.5 months.
B) CV = +$5,000
C) Cost Estimate at Completion EACcost) ) = $32,000
D) CPI = 1.33
E) SV% = 1.2

Correct Answer:

verifed

Verified

Unlock this answer now