Multiple Choice
Which of the following is/are sources of influence that can cause actual project performance to differ from planned performance?
A) Pareto's Law
B) Moore's Law
C) Murphy's Law
D) The Law of Large Numbers
E) Little's Law
F) All of the Above
G) None of the Above
H) A and C only
Correct Answer:

Verified
Correct Answer:
Verified