Multiple Choice
If today is manufacturing day 100 and an order has a due date of 120 and a lead time remaining of 25 days, the critical ratio would be:
A) 0.8
B) 1.2
C) 1.25
D) 0.25
E) 0.2
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q22: All of the following are elements of
Q23: An order for 100 of a product
Q24: Given the following information, which sequence
Q25: Which file contains information on the efficiency
Q26: Operation overlapping means:<br>A) using alternate routings<br>B) moving
Q28: The selection and sequencing of available jobs
Q29: Planning the flow of work requires production
Q30: The activities of production activity control can
Q31: Which of the following is NOT a
Q32: Which of the following statements is true?<br>I.