Multiple Choice
An order for 100 of a product is processed on work center 123. The setup time is 60 minutes and the run time is 5 minutes per piece. If the order is run on two machines in the work center, and the setups are made simultaneously, the elapsed time will be:
A) 560 minutes
B) 500 minutes
C) 250 minutes
D) 310 minutes
Correct Answer:

Verified
Correct Answer:
Verified