Given the Following Data, Which Job(s) Will Be Late If

Question 20

Multiple Choice

Given the following data, which job(s) will be late if the shortest process time sequencing rule is used?
Today is day 100.
 Job  Process  Time  Due  Date  A 4104 B 1106 C 5109\begin{array} { l l l } \text { Job } & \begin{array} { l } \text { Process } \\\text { Time }\end{array} & \begin{array} { l } \text { Due } \\\text { Date }\end{array} \\\text { A } & 4 & 104 \\\text { B } & 1 & 106 \\\text { C } & 5 & 109\end{array}


A) all jobs will be on time
B) A and B will be late
C) A and C will be late
D) B and C will be late

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge