Multiple Choice
Given the following data, which job(s) will be late if the shortest process time sequencing rule is used?
Today is day 100.
A) all jobs will be on time
B) A and B will be late
C) A and C will be late
D) B and C will be late
Correct Answer:

Verified
Correct Answer:
Verified