Multiple Choice
Which of the following is an assumption made by the critical path method (CPM)
A) The activity time estimates are accurate and stable.
B) Activities are dependent on each other, without clearly defined start and finish times.
C) Activities are interrupted many times before completion.
D) The project network defines a tentative work sequence that can be changed anytime during the project.