Multiple Choice
Which of the following is true of the Critical Path Method (CPM)
A) It allows us to investigate the effects of uncertainty of activity times on project completion times.
B) It uses the variance in the critical path activities to evaluate the risks associated with project completion times.
C) It assumes that activities are independent of one another, with clearly defined start and finish dates.
D) It accounts for the interruptions that may affect an activity between the start and the finish times.
Correct Answer:

Verified
Correct Answer:
Verified
Q5: _refers to reducing the total time to
Q6: In the context of the Critical Path
Q7: The district magistrate of a city has
Q8: In the project management life cycle, the_involves
Q9: Implementing a new computer-aided design system is
Q11: Which of the following is an assumption
Q12: In the context of the Critical Path
Q13: The activities, their respective immediate predecessors,
Q14: A pure project organizational structure eliminates the
Q15: In the context of project management,_a project