Multiple Choice
The district magistrate of a city has decided to reconstruct the most frequented street of the city. He plans to block the street for the duration of the work, which will cause considerable inconvenience to the people of the city. The project has three parallel paths defined as the following:
Path A-B-C-H will take 16 days.
Path A-D-E-H will take 22 days.
Path A-F-G-H will take 30 days.
In the given scenario, which of the following statements is true?
A) The expected duration of the project is 68 days.
B) Activities B, D, and F have an earliest starting time of 0.
C) Path A-D-E-H has the largest slack time.
D) Path A-F-G-H is the critical path.
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Rose is in charge of advertising
Q3: In the context of projects,_are discrete tasks
Q4: Project managers do not need technical expertise.
Q5: _refers to reducing the total time to
Q6: In the context of the Critical Path
Q8: In the project management life cycle, the_involves
Q9: Implementing a new computer-aided design system is
Q10: Which of the following is true of
Q11: Which of the following is an assumption
Q12: In the context of the Critical Path