Multiple Choice
Consider a work center with a demand rate of 50 parts per hour and using a container that can hold 12 parts. It is estimated that the container takes 1 hour to cycle through the work cell. Assume a safety stock level of 10 percent. What is the value of D for this system?
A) 50
B) 12
C) 1
D) 0.1
Correct Answer:

Verified
Correct Answer:
Verified
Q63: Proper workplace cleaning and maintenance would be
Q64: SMED is most closely related to which
Q65: Lean thinking with a firm's suppliers involves
Q66: Lean systems are also known as?<br>A) Push
Q67: Consider a work center with a demand
Q69: Consider a work center with a demand
Q70: If you calculate the number of containers
Q71: Consider a work center with a demand
Q72: Much of the Toyota Production System was
Q73: Lean concepts are rarely used in service